Every permit and zoning event in one metro, reconciled to pipeline stage

About this product

Sold by
Capitol Bend Realty Data, under its own name
Sold to
Multifamily developers and construction lenders underwriting Austin supply
Sold as
An add on to the Supply Ledger subscription, priced by the firm
Cadence
Monthly, in the second week
Built from
City of Austin permits data, zoning and site plan cases, TDHCA tax credit applications and appraisal records
Compared with
The firm's quarterly Central Texas Supply Ledger
Produced by
Axe, every edition
Signed off by
The firm's Director of Supply Research

Capitol Bend Realty Data

Development Pipeline MonitorNo. 9 · October 2026

Development Pipeline Monitor · Austin multifamilyData to September 30, 2026

Deliveries outrun starts for a sixth straight quarter

Austin delivered 5,000 multifamily units in the third quarter and started 1,800. The units under construction fell by 3,200, while new zoning cases rose for the first time since 2024

1Where the pipeline stands

We track 63,000 multifamily units across five stages, from an open zoning case to a building under construction. The total is 3,600 units lower than at the end of June. Units under construction account for 3,200 of that fall, as buildings permitted in 2023 and 2024 finished and too few new ones broke ground to replace them.1

Table 1Multifamily pipeline by stageunits
StageSep 2026Jun 2026Change
Zoning case14,20013,100+1,100
Site plan filed11,80012,400down 600
Site plan approved8,9009,300down 400
Permitted, not started6,4006,900down 500
Under construction21,70024,900down 3,200
Austin63,00066,600down 3,600

Source: City of Austin issued construction permits and site plan cases, Travis County appraisal records, TDHCA applications, Capitol Bend Realty Data estimates

Figure 1Units starting construction and units delivered, monthlyunits

Source: City of Austin issued construction permits and site plan cases, Travis County appraisal records, TDHCA applications, Capitol Bend Realty Data estimates

2Entitlement events in September

We recorded 41 entitlement and permit events on multifamily projects in September. The five below moved the most units. One project on South Congress cut its announced count from 310 to 264 units at site plan; we keep both figures and count the revised one.2

Table 2Largest multifamily events in Septemberunits
ProjectSubmarketUnitsEventCounted at
East Riverside towerSoutheast412Site plan approvedSite plan approved
Domain area podiumNorth356Building permit issuedPermitted
South Congress midriseSouth310 to 264Units revisedSite plan filed
Mueller area infillCentral240Site plan filedSite plan filed
Family tax credit projectNortheast180TDHCA 4% bond applicationZoning case

Source: City of Austin permits and development case records, TDHCA application log, September 2026

3Where the unbuilt pipeline sits

Of the 41,300 units not yet under construction, 9,800 sit in the Southeast submarket, most of them along East Riverside and in the airport corridor. The Northwest holds the fewest, at 4,000, after two years in which almost no new zoning cases were filed there.

Figure 2Units not yet under construction, by submarketunits, zoning case through permitted
Southeast
9,800
North
8,600
East
7,400
South
6,300
Central
5,200
Northwest
4,000

Source: City of Austin issued construction permits and site plan cases, Travis County appraisal records, TDHCA applications, Capitol Bend Realty Data estimates

4Revisions between stages

We keep the unit count a developer first announced and every later revision. In the third quarter, 19 projects changed their counts, all downward, by a combined 640 units. Site plan is where most revisions happen, usually when parking, fire access or a lender's sizing forces a smaller building.

Table 3Projects revised in the third quarterprojects and units
Stage at revisionProjectsAnnouncedNowChange
Zoning case62,1401,980down 160
Site plan filed93,3202,910down 410
Site plan approved41,4601,390down 70
All revised196,9206,280down 640

Source: City of Austin issued construction permits and site plan cases, Travis County appraisal records, TDHCA applications, Capitol Bend Realty Data estimates

5Against the Supply Ledger

6What to watch in October

Whether the three East Riverside zoning cases reach Planning Commission before the holidays, how many of the 6,400 permitted units start before permits begin to expire, and the TDHCA board's next round of 4 percent bond determinations.

How this monitor is built

  • Every project is placed at the furthest stage supported by a public record, using the firm's own stage definitions
  • Announced units are kept as first filed, with every revision dated and the latest figure counted
  • Each event traces to a permit, case number or TDHCA application held on file for subscribers who ask

Approved for subscribersDana WhitcombDirector of Supply Research · October 8, 2026

1 Multifamily means five or more units in one building. Under construction starts at the first passed foundation inspection and ends at a certificate of occupancy.

2 Tax credit projects are placed by their city record; a TDHCA application alone does not move a project to a later stage.

Development Pipeline Monitor · For subscribers of the Central Texas Supply LedgerCapitol Bend Realty Data